Using Resource Costs in Resource Journals and Job Journals

You can post the usage of a resource in a resource journal or a job journal. Entries posted in a resource journal have no effect on the general ledger.

To Use Resource Costs in Resource Journals and Job Journals:

  1. Open the Resource Journal window.

  2. In the Work Type Code field, on the first line, select a work type.

  3. Fill in the journal lines with the relevant information. For Help about a specific field, click the field and press F1.

  4. After filling in the fields, click Posting, Post to post the journal.

Related Topics

Setting Up Resource Costs

Calculate Job WIP Value Batch Job

Post Job WIP Value to G/L Batch Job

Calculate Job Recognition Batch Job

Post Job Recognition to G/L Batch Job