Using the Manufacturing Batch Unit of Measure

If an item is stocked in one unit of measure but produced in another, the program can create a production order that uses a manufacturing batch unit of measure to calculate the correct quantity of the components during the Refresh Production Order batch job. An example of the manufacturing batch unit of measure calculation is when a manufactured item is stocked in pieces but produced in tons.

To Create a Production BOM using the Batch Unit of Measure:

The manufacturing batch unit of measure is used as the Unit of Measure Code on the Production BOM header. Once the header is completed, the component lines are added, using quantities that reflect the amount needed to produce the item in the designated batch unit of measure.

  1. The manufacturing batch unit of measure is set up as an alternative unit of measure in the Item Units of Measure window on the item to be produced. The batch unit of measure will not replace the Base Unit of Measure on the item.

    1. If it doesn't already exist, you may need to add the manufacturing batch unit of measure code to the Units of Measure window.

  2. Create a Production BOM for the item set up with the manufacturing batch unit of measure.

    1. In the Unit of Measure Code field, click the AssistButton and select the manufacturing batch unit of measure.

    2. For each Production BOM line, in the Quantity Per field, enter the quantity of this component item, required to create this batch unit of measure.

  3. Open the Item Card for the related item.

    1. Click the Replenishment tab and in the Production BOM No. field, click the AssistButton and select the Production BOM created above.

  4. Create a production order header using the item set up with the manufacturing batch unit of measure.

    1. Click Functions, Refresh and click OK.

To view the results, click Lines, Components. The program calculates the correct quantity of the components needed to satisfy the production BOM based on the manufacturing batch unit of measure.

To Calculate a Manufacturing Batch Unit of Measure on a Production Order:

While the manufacturing batch unit of measure is set up on the Production BOM, it can also be set up on production orders that require a unit of measure that is different than the one specified on the Production BOM.

  1. Create a production order header using the item set up with the manufacturing batch unit of measure.

  2. In the Item No. field in the Production Order line, type the same item number used in the header.

  3. In the Quantity field, enter the same quantity used in the header.

  4. In the Unit of Measure Code field, click the AssistButton and select the manufacturing batch unit of measure code.

  5. Click Functions, Refresh.

    1. Click the Options tab and in the Calculate option, uncheck the Lines field.

    2. Click OK.

To view the results, click Lines, Components. The program calculates the correct quantity of the components needed to satisfy the production BOM based on the manufacturing batch unit of measure.

Related Topics

Calculating Lines from Production Order Headers

Calculating Production Order Components

Processing Production Orders

Refreshing a Production Order

Units of Measure



© 2009 Microsoft Corporation. All rights reserved.