Previous Operation No. Field

The Routing Line Table

This field shows the previous operation number, which is automatically assigned by the program.

The previous operation number indicates the operation, which was run directly before the actual operation.

Example:

If operation 30 has the entry 10 in this field, it means that operation 10 must be run directly before this operation.

Several operations may have the same previous operation number because several operations can follow an operation due to the parallel operations facility.