The Prod. Order Routing Line Table
This field shows the sequence number (backward).
It is possible to plan a production order with forward and backward calculation. Depending on the planning, sequence numbers are assigned. Here the sequence number is entered which this operation has in the backward planning.
Example:
OP1 | OP2 | OP3 | OP4 | OP5 | OP6 |
6 | 5 | 4 | 3 | 2 | 1 |
*OP stands for operation - the numbers in the line below correspond to the sequence number in the backward calculation.
To see the difference between forward and backward calculation in the range of sequence numbers, click here.