You can use the Refresh Planning Demand batch job to refresh the planning components and the routing lines for the current planning line.
Open the Planning Worksheet window.
In the Planning Worksheet window, select the line you want to refresh.
Click Functions, Refresh Planning Line.
On the Planning Line tab, the filters are prepared for the current Lot No. field.
On the Options tab you can make the following selections:
Scheduling Direction |
Forward |
Scheduling starts from the starting date and proceeds forward (to the finishing date). |
|
Back |
Scheduling starts from the ending date and proceeds backward (back to the required starting date). |
Calculate |
Routings |
Place a check mark in the field to refresh the planning routings. |
|
Component Need |
Place a check mark in the field to refresh the planning components. |
Click OK to confirm your selections.