Entering Master Data for Output Posting

To post work progress automatically, you must assign a flushing method to the machine center or the work center.

To Enter Master Data for Output Posting:

  1. Open the Machine Center Card window.

  2. Fill in the Flushing Method field on the Posting tab. You can choose from the following options:

    Flushing Method

    Manual

    Manual posting of consumption in the output journal.

     

    Forward

    Automatic posting of planned run time and output quantity upon releasing the production order.

     

    Backward

    Automatic posting of planned run time and output quantity upon finishing the production order.

  3. Enter the flushing method on the work center card as well, by clicking Cap. Reqts. Planning, Work Centers.

Related Topics

Posting Output Quantity

Posting Run Time