Action Message Field

The Requisition Line Table

In this field, the program proposes an action for the user to take in order to rebalance the current demand-supply situation. The program may propose one of the following options for a planning line:

New

Create a new order.

Change Qty.

Change the quantity on an existing order.

Reschedule

Reschedule the due date on an existing order.

Resched. & Chg. Qty.

Reschedule the due date and change the quantity on an existing order.

Cancel

Cancel an existing order.

Attention

Released production orders with no consumption or output posting may also be cancelled. To avoid this, set the planning flexibility of released production orders to None.