Capacity Task List Report

This report shows the production orders that are waiting to be processed at the work centers and machine centers. Printouts are made for the capacity of the work center or machine center). The report includes information such as starting and ending time, date per production order and input quantity.

You can define what is included in the report by setting filters. You can set additional fields on the Prod. Order Routing Line tab by clicking the Field field, then clicking the AssistButton that appears to the right. Fill in the fields as follows:

Prod. Order Routing Line

Type: Here you can select whether you want to create the list for a Work Center or a Machine Center.

No.: Here you can enter the number of the desired work or machine center.

Status: Here you can define whether the load is only to be created for a certain status of the production order.

Starting Date: Here you can enter the starting date from which the list is to be created.

Click the up-arrow at the lower left-hand corner of the window to see the result of the filters you have defined for the table.

Click Print to print the report. If you want to see the report on the screen before printing, click Preview. If you do not want to print the report now, click Cancel to close the window.