Replan Production Order Batch Job

With this batch job, you can recalculate the calculated production orders.

The production order BOM is generated from the item production BOM calculation. The program copies the production routing into the production order line from the item routing. These entries are checked and recalculated.

Attention

Manual entries can be overwritten.

You can determine what is shown in the batch job by filling in the fields on the Options tab. Fill in the fields as follows:

Options

Scheduling Direction: Define whether you want the scheduling to be replanned forward or backward.

Forward scheduling begins at the starting date and proceeds forward to the finishing date. Backward scheduling begins from the ending date and proceeds backward to the required starting date.

Plan: Here you can define whether the planning is to take place over one or all levels of the production BOM.

Click OK to start the batch job. If you do not want to run the batch job now, click Cancel to close the window.